Mbudzi Interchange Finally Opens After Delays and Budget Controversy

After numerous delays and budget overruns, Harare’s Mbudzi Interchange finally opens to traffic on May 30, 2025. The project, initially scheduled for completion in 2023, has faced intense scrutiny over its ballooning $88 million price tag and extended timeline.

Transport officials initially promised a 12-month construction period when announcing the project in late 2021. However, work only commenced in September 2022 after the closure of the problematic traffic circle connecting Simon Mazorodze, Chitungwiza, and High Glen roads.

The government later revised the completion estimate to 18 months, projecting an opening in March 2024. The finished interchange arrives more than a year past this adjusted deadline, leaving many questioning the project management.

ALSO READ: Nestlé Injects $7 Million Into Zimbabwe To Boost Cerevita Production

Mbudzi Interchange Finally Opens

The interchange’s final cost has become a hot topic in Zimbabwean political circles. Initial estimates from engineering firm DNMZ suggested $65 million would cover construction, but the final bill reached $88 million after additional expenses were included.

These extra costs covered:

  • Detour road construction
  • Property compensation
  • Professional service fees
  • Unspecified additional expenses

Regional Cost Comparisons Raise Questions

During recent Senate hearings, legislators highlighted stark price differences between Zimbabwe’s interchange and similar regional projects. Matabeleland North senator Sengezo Tshabangu noted that South Africa’s massive Mount Edgecomb interchange – the largest in the southern hemisphere – cost $11 million less than Mbudzi.

Transport Minister Felix Mhona attributed the higher costs to Zimbabwe’s “unique” economic situation, citing international sanctions and local price fluctuations for construction materials such as cement.

ALSO READ: Construction Mogul Takes Legal Action Over $450k Unpaid Development Fees

Additional Controversies Surrounding the Project

The interchange, officially named “Trabablas” after President Emmerson Mnangagwa’s war name, has been marred by additional controversies:

  • Non-competitive tender process for the construction consortium
  • Recent arrests for fraudulent compensation claims
  • Ongoing questions about financial accountability

As the interchange finally opens to relieve Harare’s notorious traffic congestion, many Zimbabweans continue to question whether the benefits justify the substantial time and financial investments.

 